Public Service

Beech Road Improvements

Most of the corridor will be widened from three to four lanes, the Jug Street intersection will be expanded to improve traffic flow, and upgrades will include new pavement, curbs, storm sewer, street lighting, and traffic signals.

Project Updates

Reconstruction of Beech Road is expected to begin in March 2027, bringing infrastructure improvements that will enhance traffic flow and support continued growth in the New Albany International Business Park. The project spans Beech Road between Smith’s Mill Road and Jug Street. Most of the corridor will be widened from three to four lanes, the Jug Street intersection will be expanded to improve traffic flow, and upgrades will include new pavement, curbs, storm sewer, street lighting, and traffic signals.

Construction is expected to be completed, with all lanes reopened, by December 2027. Final touches and landscaping improvements are planned for spring 2028.

Overhead satelite view of Beech Road with text reading "Beech Road Improvement Project"

Frequently Asked Questions

When will construction begin on Beech Road?

After hiring a contractor, we reevaluated the proposed schedule and anticipated traffic impacts and decided to begin detours in March 2027. Some “offline” work will begin this fall, including storm sewer installation and other work outside the existing roadway. Impacts to travel lanes are expected to be short-term and minimal. Construction is expected to be completed, with all lanes reopened, by December 2027. Final touches and landscaping improvements are planned for spring 2028.

Why are you widening onto private property instead of to the east?

All widening work is within the public right-of-way, with a couple of exceptions around intersections. Our design team prioritized widening to the east, but some limited widening to the west is necessary to maintain proper lane widths.

What will happen to roof drains that outlet into the ditch?

Storm drains, drainage tiles, and septic aerator discharge pipes that outlet into the ditch will be extended and connected to the storm sewer at the project’s expense. We will work with affected property owners to locate these lines and install a cleanout where necessary.

What is the City’s process for reviewing and establishing survey controls for construction drawings?

The centerline of Beech Road was recorded in 1999 based on the position of the roadway at the time.  The right of way width for Beech Road is documented in the Licking County Road Record Book 3 Page 158 as 60-feet wide and is centered on the roadway. While the roadway centerline has changed since 1999 by way of various roadway improvements, the right of way alignmentrecorded in 1999 by the county auditor has not changed. Multiple survey control points are referenced in each professional survey and construction project. The demolition or removal of one or many control points does not impact the ability of a professional surveyor to establish control for a survey or project.

Will the project improve traffic at the Jug and Beech intersection?

Yes. Traffic at the Jug and Beech intersection will be improved by creating additional eastbound, southbound, and northbound turn lanes on Jug Street. We are working with our contractor to complete this work as early as possible to expedite these traffic benefits.

When will the potholes on Beech Road be addressed?

The potholes on Beech Road will be repaired in October 2026 as part of the 2026 Street Improvements Program. This will provide a temporary fix until major roadway reconstruction begins in 2027.