Crosswalk Maintenance October 3-14

Crews have been performing brickwork on six different brick crosswalks around Market Square and Market and Main streets.

Brick crosswalk repair is scheduled to continue October 11-14 in the Village Center, weather permitting. While work the week of October 3 focused on Market Street, the work the week of October 11 will target Main Street. Work zones will be closed between 9 a.m. and 4 p.m. Message boards will be posted around the Village Center vicinity and updated daily alerting motorists and pedestrians about the work.

Work is scheduled to take place in the following work zones:

Work Zone Day 5 

Work is scheduled to be performed on Tuesday, October 11 in this area only. The road will be closed in this work zone. On-street parking will be temporarily blocked off on the day of work.

Work Zone Day 6 

Work is scheduled to be performed on Wednesday, October 12.  Road will be closed in this work zone. On-street parking will be temporarily blocked off on the day of work.