A Smoother, Safer Commute

Street Improvements

Discover upcoming street improvements aimed at creating safer, more efficient roads for our growing community.

About

The City of New Albany’s 2024 Street Improvement Project kicked off on July 16, consisting of crack fill, mill and overlay, curb replacement, ADA ramp replacement, and limited pavement rejuvenator.

Shelly and Sands is the contractor for the project. On this page, you will find maps with all streets identified and the planned improvements noted.

The project is expected to be substantially completed by December 1, 2024, while minor punch work may occur in early 2025. We will be reaching out to affected residents directly as the work progresses to ensure everyone is aware of the project’s impacts in a timely manner. However, please continue to review this webpage as the project develops for the latest and most current updates.

Latest News

Upcoming Schedule

The City of New Albany Street Improvement Project for 2024 is entering its final stages. The paving portion of the project should be complete by 10/4. Here is the schedule for the week of 9/30. 

Thursday, 10/3 – Fabric and Paving Walton Parkway

Friday, 10/4 – Fabric and Paving Walton Parkway

Saturday, 10/5 – Paving Sugarwood, Camile, Jersey, Decker, and Triplett

Monday, 10/7 – Paving Sugarwood, Camile, Jersey, Decker, and Triplett

The crack sealing portion of our Street Improvements Project on major arterial roads (US-62, SR 605, Smith’s Mill Road, etc.) will be performed outside of rush hour traffic to minimize traffic impacts. The work is weather dependent and subject to change.

 

Anticipated Project Schedule

The dates on the document are tentative, and we will update them regularly. The contractor and the City’s inspection team will also be distributing notices to the affected residents within 7-days of and 24-hours prior to the start of work. A full-time City representative will be on-site to answer any questions or receive comments and concerns. Please continue to reference the website for regular project updates.

street maintenance map

18" Concrete Curb

The City’s contractor, Shelly & Sands, began with curb repair work in the Planters Grove area on July 16 (location 6 in this exhibit).The dates on the exhibit are tentative, and we will update them regularly. The contractor and the City’s inspection team will also be distributing notices to the affected residents within 7-days of and 24-hours prior to the start of work. A full-time City representative will be on-site to answer any questions or receive comments and concerns. The City-wide street improvement project is expected to be completed by December 1, 2024, while work in section 6 is expected to be completed by mid-August. Please continue to reference the website for regular project updates.

street crack fill map

Street Crack Fill

street reclamite map

Street Reclamite

Contact

For any questions or concerns, please reach out to Jordan Gambill with New Albany Public Service at 614.855.0076 or jgambill@newalbanyohio.org.