We are in the final phase of construction on New Albany’s US 62 improvement project. The project began in October 2022.
All of the underground wiring is now complete for the mast arms and traffic signal systems, which began to be installed the first week of December 2023. We are now only waiting for the permanent traffic signal heads, but everything else will be installed in the coming weeks. We are now expecting this work to be completed by mid-February.
Follow Us & Use #newalbanyohio
3 days ago
Photo
Share on Facebook Share on Twitter Share on Linked In Share by Email
3 days ago
Photo
Share on Facebook Share on Twitter Share on Linked In Share by Email
3 days ago
Photo
Share on Facebook Share on Twitter Share on Linked In Share by Email
4 days ago
Photo
Share on Facebook Share on Twitter Share on Linked In Share by Email
4 days ago
Photo
Share on Facebook Share on Twitter Share on Linked In Share by Email