Street Improvements

About

We are pleased to announce that the City of New Albany’s 2024 Street Improvement Project is scheduled to kick off on July 16, starting in the Planters Grove area (see the 18″ Concrete Curb section on this page for more information). Shelly and Sands will be the contractor for the project. The 2024 Street Improvement project will consist of crack fill, mill and overlay, curb replacement, ADA ramp replacement, and limited pavement rejuvenator. On this page, you will find maps with all streets identified and the planned improvements noted.

The project is expected to be substantially completed by December 1, 2024, while minor punch work may occur in early 2025. We will be reaching out to affected residents directly as the work progresses to ensure everyone is aware of the project’s impacts in a timely manner. However, please continue to review this webpage as the project develops for the latest and most current updates.

Anticipated Project Schedule

To access a PDF that includes the proposed schedule for the various stages of the project, click here.

The dates on the document are tentative, and we will update them regularly. The contractor and the City’s inspection team will also be distributing notices to the affected residents within 7-days of and 24-hours prior to the start of work. A full-time City representative will be on-site to answer any questions or receive comments and concerns. Please continue to reference the website for regular project updates.

Mill and Overlay

Click here to access a fullscreen PDF of the map. Additional details coming soon.

Street Crack Fill

Click here to access a fullscreen PDF of the map. Additional details coming soon.

Street Reclamite

Click here to access a fullscreen PDF of the map. Additional details coming soon.

18" Concrete Curb

Click here to access a fullscreen PDF of the map.

The City’s contractor, Shelly & Sands, is scheduled to begin with curb repair work in the Planters Grove area on July 16 (location 6 in this exhibit).The dates on the exhibit are tentative, and we will update them regularly. The contractor and the City’s inspection team will also be distributing notices to the affected residents within 7-days of and 24-hours prior to the start of work. A full-time City representative will be on-site to answer any questions or receive comments and concerns. The City-wide street improvement project is expected to be completed by December 1, 2024, while work in section 6 is expected to be completed by mid-August. Please continue to reference the website for regular project updates.

Contact

For any questions or concerns, please reach out to Jordan Gambill with New Albany Public Service at (614) 855-0076 or jgambill@newalbanyohio.org.