Open grassy field with a row of trees in the distance and tall electrical transmission towers and power lines crossing under a blue sky with scattered clouds

News

AEP Souder Transmission Line Project

AEP Ohio representatives are upgrading the electric power grid in the New Albany area through the construction of a new substation and transmission line project in Franklin County.

The existing electrical network in this area has reached capacity. The new transmission line and substation will provide an additional power source to help ensure reliable electric service for residential and commercial customers while supporting continued economic development in the area.

The City of New Albany understands and appreciates the concerns residents have shared regarding the appearance and placement of the new transmission poles associated with the AEP Souder Transmission Line Project. 

While the project is taking place within New Albany, the transmission line is an infrastructure project led by AEP Ohio and regulated by the Ohio Power Siting Board (OPSB), which has jurisdiction over the approval, routing, and placement of high-voltage transmission facilities in Ohio. Under Ohio law, local municipalities have very limited authority over transmission line routing and pole placement decisions once a project falls under OPSB jurisdiction. The OPSB reviews applications, evaluates routing options, considers environmental and engineering impacts, and ultimately determines whether a project may proceed. The Souder Transmission Line Project received OPSB approval in October 2025.

Although the City does not control the final placement of the poles, City staff did communicate with AEP representatives throughout the process and shared community feedback and concerns when possible. However, final decisions are made by AEP and the OPSB.

The City of New Albany understands some residents remain frustrated by the visual impact of the infrastructure. The City will continue to encourage AEP to be responsive to residents throughout the remainder of construction and restoration activities.

Project Overview

The project includes:

  • Construction of the new Souder Substation off Souder Road in New Albany
  • Construction of just over one mile of new 138-kilovolt (kV) transmission line
  • Development of an approximate 100-foot right-of-way corridor for the transmission line
  • Acquisition of new easements to support the safe construction, operation and maintenance of the line

Project Timeline

  • Summer 2025: Project publicly announced
  • 2025: Application submitted to the Ohio Power Siting Board (OPSB)
  • October 2025: OPSB approval received
  • January 2026: Construction began
  • Summer 2026: Transmission line construction anticipated to conclude
  • Fall 2026: Additional substation work expected to continue

Construction Information

Construction crews began work in early 2026 and will continue through summer 2026, with additional station-related work planned into fall 2026.

Residents and motorists may notice construction activity in the project area throughout the duration of the work.

From June 5 to June 12, drivers should expect short delays during a single-lane closure on East Walnut Street. Please follow the direction of flaggers when passing through the work zone.

Questions or Additional Information

Residents with questions regarding construction activities or upcoming work may contact:

Joseph Greene
OR Colan
Phone: 614-340-8233
Email: JGreene@orcolan.com

For additional project information from AEP Ohio,  please visit: https://www.aeptransmission.com/ohio/Souder/

Click here to access AEP’s notification letter.

Stylized map showing a blue route from a shaded polygon in the southwest to Rocky Fork Metro Park and E Walnut St in the northeast.
This map shows where the AEP project will be taking place.
Share the Post:

Related Posts